An office budget is shaped by the space, the work and the way your team will use it.
Partitions, workstations, lighting and storage come together to create a working environment. The price becomes useful when you can see what each part includes. A single total leaves too much to assumption.
Here is a worked example showing how a brief becomes a scope, how a scope becomes a quotation, and how to compare the numbers without losing the detail.
All quantities and prices in this example are fictional and chosen to make the calculation easy to follow. They are not Kolkata market rates or a Roy Constructions quotation.
Start with a brief that describes the office
A brief is a simple description of what you need. It connects the budget to daily use before materials and finishes are selected.
Part of the brief | Illustrative requirement |
|---|---|
Location | A hypothetical office in Kolkata |
Area | 1,000 sq.ft of carpet area, meaning usable internal floor area for this example |
Team | 12 workstations, with chairs purchased separately |
Rooms | One meeting room and one open working area |
Storage | Four fitted storage units |
Existing finishes | Retain the existing floor and ceiling, subject to inspection |
Electrical and lighting | 24 socket points and 12 light fittings in the example schedule; actual requirements need assessment |
Separate appointments | Chairs, IT equipment, data cabling, AC work and specialist systems |
Completion requirement | A proposed occupation date, checked against access, approvals, procurement and the agreed work |
For this example, the storage units are each 1.2 m wide, 0.45 m deep and 0.9 m high. The workstation tops are each 1.2 m wide and 0.6 m deep. These dimensions only define what the fictional prices refer to. They are not a space-planning recommendation.
The actual design should establish the sizes and clearances your office needs. The brief gives that conversation a starting point.
Turn the brief into a scope of work
The scope describes what the contractor is being asked to deliver. It also records what sits outside the appointment.
Work package | Included in this example | Detail to settle before a real quotation |
|---|---|---|
Partitions | Supply and installation of 300 sq.ft of partition work, measured on one face | Approved drawing, height, construction, finish, openings and any performance requirement |
Painting | Preparation and painting of 2,000 sq.ft of agreed wall surfaces | Existing condition, repair extent, coating system and finish |
Workstations | Supply and installation of 12 desk units, at the example dimensions | Construction, finish, support, cable openings and layout |
Storage | Supply and installation of four fitted units, at the example dimensions | Internal layout, board specification, shutters, finish and hardware |
Lighting | Supply and installation of 12 fittings | Product schedule, locations and associated electrical scope |
Socket points | 24 points within the defined example package | Wiring routes, fittings, supply boundaries and checks, specified by the responsible professional |
Site protection | Protection of the retained finishes during the agreed work | Areas, method and responsibility for removal |
Completion cleaning | Cleaning associated with this appointment | Included areas and standard of cleaning |
Chairs, IT equipment, data cabling, AC changes and specialist systems are outside this sample contract. They are not assumed to cost nothing. The business would need separate prices for the items it requires.
This is a teaching outline. A real scope needs the approved drawings and specifications behind it. For example, a meeting room needs a clear decision about its door and any privacy requirement; neither is established by the word “partition”. No separate door is priced in this example.
Build the BOQ from the agreed work
A bill of quantities, or BOQ, is the itemised list of work, measurements and prices. It lets you see how the total is formed.
Fictional sample BOQ. Amounts exclude tax. Rates are arbitrary teaching figures, not prices to use for procurement.
Item | Quantity | Unit | Sample rate | Sample amount |
|---|---|---|---|---|
Partition work | 300 | sq.ft of partition surface | ₹200 | ₹60,000 |
Wall painting | 2,000 | sq.ft of wall surface | ₹25 | ₹50,000 |
Workstation desk units | 12 | units | ₹18,000 | ₹2,16,000 |
Fitted storage units | 4 | units | ₹20,000 | ₹80,000 |
Light fittings | 12 | fittings | ₹1,500 | ₹18,000 |
Socket points | 24 | points | ₹1,200 | ₹28,800 |
Site protection | 1 | agreed package | ₹20,000 | ₹20,000 |
Completion cleaning | 1 | agreed package | ₹7,200 | ₹7,200 |
Sample contract subtotal | ₹4,80,000 |
Each line follows the same calculation. Four storage units at ₹20,000 each give ₹80,000. Twelve workstation units at ₹18,000 each give ₹2,16,000.
The 1,000 sq.ft floor area does not replace the measurements in the BOQ. Painting uses wall surface area in this example. Partitions use their own stated measurement basis. Desks and storage use unit counts. These are different things being priced.
Compare the same finished result
Suppose two fictional proposals use identical specifications and rates for the shared work. Proposal A leaves out storage. Proposal B includes it.
Comparison | Proposal A | Proposal B |
|---|---|---|
Shared sample work | ₹4,00,000 | ₹4,00,000 |
Four storage units in the original quote | Excluded | ₹80,000 |
Quoted subtotal, before tax | ₹4,00,000 | ₹4,80,000 |
Storage added to make the scopes match | ₹80,000 | Already included |
Comparable subtotal, before tax | ₹4,80,000 | ₹4,80,000 |

Proposal A has the lower opening figure. Once the same storage is included, both reach the same subtotal. In this example, the apparent difference comes entirely from omitted work.
In a real comparison, the rates and specifications may differ too. Ask for those differences to be explained rather than assuming that the same item name means the same product.
Read the per-square-foot figure in context
The sample subtotal of ₹4,80,000 divided by the example’s 1,000 sq.ft carpet area gives ₹480 per sq.ft. That is arithmetic for this fictional package. It is not a market rate, and it still excludes the separate purchases and tax.
If someone divides that same subtotal by an advertised area of 1,250 sq.ft instead, the figure becomes ₹384 per sq.ft. The work and total have not changed. Only the denominator has changed.
Same sample contract | Area used for the calculation | Calculated figure |
|---|---|---|
₹4,80,000 before tax | 1,000 sq.ft carpet area | ₹480 per sq.ft |
₹4,80,000 before tax | 1,250 sq.ft advertised area | ₹384 per sq.ft |
Ask which area is being used and what the package contains before comparing rates.
Keep the full business budget visible
The sample contract subtotal is only part of the spend. Chairs, IT, data cabling, AC changes, specialist requirements and any building charges still need to be checked and priced where applicable. Confirm the tax treatment in the actual proposal.
No allowance for those items is invented here. An unanswered cost should remain visible until it has a basis.
Bring your floor plan, photographs and working requirements to Roy Constructions. A clear brief gives the budget structure. An agreed scope gives the number meaning.
Compare two quotes on the same scope
Illustrative comparison for a vacant 2,000 sq ft carpet-area office. Both samples assume a usable floor base and existing base-building HVAC and fire systems. The amounts are invented to demonstrate quote comparison and are shown before GST.
Sample A includes ₹20 lakh for 2,000 sq ft of vinyl flooring, 1,200 sq ft of gypsum ceiling, 600 sq ft of gypsum partitions, 3,000 sq ft of painting, six door sets, an electrical and data package with 24 power points, 24 LED fixtures and 12 data points, and site protection and handling. Add 120 running ft of fixed storage at ₹2.40 lakh and 20 workstation sets at ₹2.60 lakh. Sample A totals ₹25 lakh.
Sample B is quoted at ₹23.80 lakh and excludes the 20 workstation sets. Adding the same ₹2.60 lakh allowance brings it to ₹26.40 lakh. Both examples exclude GST, design and approval fees, HVAC and fire modifications, major substrate repairs, IT hardware, loose seating and contingency.